Rooftop solar on a sectional title scheme: who must you register with?

It depends on size and grid connection, not on whether power is exported. A grid-connected system of 100 kW or less registers with the distributor, Eskom or the licensed municipality. A grid-connected system above 100 kW registers with NERSA. A system with no grid connection is exempt from registration.

By the Dev 360 teamNovember 2026South African context
Installer fitting solar panels on residential roofs

Key takeaways

  • Registration depends on capacity and grid connection
  • 100 kW or less: register with Eskom or the municipality
  • Above 100 kW: register with NERSA
  • Roofs are common property: the body corporate must approve

The registration rule

NERSA clarified in 2026 that the duty to register an embedded generation facility depends on whether it has a point of connection to the grid and its installed capacity. Facilities of 100 kW or less with a grid connection register with the relevant distributor; those above 100 kW register directly with NERSA; facilities without a grid connection are exempt.

Approvals inside the scheme

Roofs are common property, so a scheme-wide installation needs the body corporate’s approval by the resolution the Sectional Titles Schemes Management Act requires, plus agreements covering use of the roof, metering, maintenance and who pays.

Energy as a service

Some schemes avoid a large special levy by having a provider install and operate the system and sell the power. Read how rooftop energy-as-a-service works, and see Dev 360’s planned Energy as a Service initiative.

Short answers

Does a sectional title solar system need NERSA registration?

Only if it is grid-connected and above 100 kW. Grid-connected systems of 100 kW or less register with Eskom or the licensed municipality; off-grid systems are exempt.

Does exporting power change the rule?

No. NERSA has clarified that registration depends on grid connection and installed capacity, not on whether electricity is exported.

Who must approve solar on a common-property roof?

The body corporate, by the resolution the Sectional Titles Schemes Management Act requires, supported by written agreements on use, metering and maintenance.