Rooftop energy-as-a-service: solar without a large special levy

Yes. With energy-as-a-service, a provider funds, installs, owns and maintains the system and the body corporate pays for the energy, so no special levy is needed for capex. It still needs the right approvals: a PMR 29 resolution for the improvement, a special or unanimous resolution if roof space is leased, municipal approval and an electrical Certificate of Compliance.

By the Dev 360 teamSouth African context
Technician in a safety harness inspecting solar panels on the roof of a sectional title complex

Key takeaways

  • The provider funds the system; the scheme pays for the energy
  • Roof leases need STSMA section 4(h) or 5(1)(a) resolutions
  • Grid-tied systems need municipal approval; larger ones need NERSA registration
  • Selling power to third parties raises licensing questions

How the model works for a scheme

  1. Assess the roof, structure, consumption and tariffs.
  2. Choose a provider and model: pay per kWh or a fixed fee.
  3. Get the owners' resolutions.
  4. The provider installs, registers and maintains the system.
  5. The scheme pays monthly from the admin fund.

The resolutions

  • Improvement: PMR 29. Reasonably necessary improvements need 30 days' notice, and a special resolution if a member asks for a meeting. Non-essential improvements need a unanimous resolution.
  • Roof lease: letting common property to an owner or occupier for under 10 years needs a special resolution (section 4(h)). A lease of 10 years or more, or to a third party, engages the unanimous-resolution rule in section 5(1)(a).

Energy rules

  • Grid-tied systems of 100 kW or less register with the municipality; larger systems generally register with NERSA
  • An electrical Certificate of Compliance from a registered contractor
  • Selling electricity to owners or commercial users depends on the arrangement, size and municipal rules, so get advice

Contract checks

Tariff and escalation, performance guarantees, roof repairs and access, insurance, term, buy-out and removal.

Dev 360's 2027 energy-as-a-service initiative explores scaling this across schemes.

Sources

Check each source’s current version before acting.

Important. Savings are estimates, not guarantees. STSMA resolutions and NERSA rules apply.

See also: The Energy as a Service initiative.

Through the PPP

Participants who deliver this

These PPP participants deliver this kind of work.

Dev 360 capability
Construction and trades

Electrical capability

Your reliable electrical contractor.

Services: Residential installations and repairs · Commercial and industrial installations · Inspections and certificates of compliance · Solar and backup power · Lighting design and LED upgrades · Earthing, bonding and lightning protection · Infrared thermography · Emergency repairs and maintenance

Not a guarantee of work. All participants

Short answers

Can a body corporate install solar without a special levy?

Yes, an energy-as-a-service or power-purchase arrangement can avoid a large special levy for system capital costs. The provider funds and owns the system while the scheme pays for energy, subject to South African approvals and electrical compliance.

What resolution is needed to lease a sectional title roof for solar?

A lease of common property to an owner or occupier for under 10 years needs a special resolution under STSMA section 4(h). Longer leases or leases to a third party engage the unanimous-resolution rule in section 5(1)(a), under South African sectional title law.

Does a sectional title solar system need NERSA registration?

Generally, grid-tied systems of 100 kW or less register with the municipality, while larger systems generally register with NERSA. Every installation needs an electrical Certificate of Compliance; confirm the current South African distributor and approval route.