PPP project preparation checklist: what must be ready before a tender

Before a PPP goes to tender, the institution must prove affordability, value for money and sensible risk transfer in a feasibility study. In South Africa, Treasury Regulation 16 sets the approvals: TA:I for feasibility, TA:IIA for procurement documents, TA:IIB for the preferred bidder and TA:III before signature. The 2025 amendments, effective 1 June 2025, streamlined smaller projects.

By the Dev 360 teamSouth African context
Highway interchange, transmission pylons and a fibre trench on the edge of an African city at dusk

Key takeaways

  • Feasibility must prove affordability, value for money and risk transfer
  • South Africa's approvals run TA:I, TA:IIA, TA:IIB, TA:III
  • Amended Regulation 16 took effect on 1 June 2025
  • Land, permits and demand data should be settled before procurement

The feasibility study must show

  • Strategic and operational benefits linked to the institution's mandate
  • Affordability within budgets, including contingent liabilities
  • Value for money compared with a public-sector option
  • Risk transfer: technical, operational and financial risks with the private party where appropriate
  • Institutional capacity to procure and manage the contract

South Africa's approvals

  1. TA:I: feasibility study approved
  2. TA:IIA: procurement documents approved
  3. TA:IIB: preferred bidder approved
  4. TA:III: final approval before signing

The amended Regulation 16, in force from 1 June 2025, rationalised approvals for smaller projects and added reporting on fiscal commitments and contingent liabilities.

The practical readiness checklist

  • Site and land rights confirmed
  • Environmental and social screening done
  • Demand and revenue study
  • Draft risk matrix and payment mechanism
  • Reference financial model
  • Stakeholder and community engagement plan

A South African benchmark

REIPPPP has procured 6,306 MW from 91 projects in bid windows 1 to 4, as at 31 December 2025, showing what a standardised, well-prepared procurement can deliver.

Sources

Check each source’s current version before acting.

Short answers

What must a PPP feasibility study prove in South Africa?

A South African PPP feasibility study must prove affordability, value for money and appropriate risk transfer. It also needs to show strategic and operational benefits and the institution's ability to procure and manage the contract under Treasury Regulation 16.

What are TA:I, TA:IIA, TA:IIB and TA:III?

They are four National Treasury approval stages for South African PPPs. TA:I covers feasibility, TA:IIA procurement documents, TA:IIB the preferred bidder, and TA:III final approval before contract signature.

When did the amended PPP regulations take effect?

The amended South African Treasury Regulation 16 took effect on 1 June 2025. It streamlined approvals for smaller projects and added reporting on fiscal commitments and contingent liabilities, so public institutions should use the current regulation when planning a PPP.